Bomax

Request A Quotation

Telephone: 0844 855 2105
Email: enquiries@bomax.co.uk

  • Home
  • Kerbs
    • Scan Kerb
    • Cycle Lane Kerb Solution
    • Granite Kassel Kerb
  • Paving
    • Domino Facette
    • Commercial Flags
  • Urbastyle Street Furniture
    • Urbastyle Concrete Benches
    • Urbastyle Concrete Bollards
    • Urbastyle Concrete Elements
    • Urbastyle Concrete Planters
    • Urbastyle Concrete Seats
  • Case Studies
    • Brighton & Hove – Footway widening
    • Regent Street – Footway widening
    • Southwark Bridge Road – Cycle way
    • Battle of Britain Visitor Centre
    • Gas Triplets, Kings Cross, London
    • Northern Promenade Whitley Bay
    • St Clare’s College Oxford
    • Scan Kerb Case Studies
      • Rail Bridge Havant
      • Hertfordshire University
      • London Olympics
      • M5 Hard Shoulder
      • A11 Ketteringham
      • Tesco Store
      • Bicester village
  • Download
    • Urbastyle Street Furniture Download
    • Scan Kerb Download
    • Paving Download
  • Resources
    • Blog
    • Glossary
    • FAQ
  • Contact Us

Tesco Store

Tesco Store, Transit Way, Plymouth, Devon

A failing timber retaining wall on the access road to Tesco, Transit Way, Plymouth meant that a new Gabion wall had to be constructed, including a new pedestrian pavement.

The contractor, Dean & Dyball, had to complete the work within a tight timescale and retain 24 hour access to the store.

The use of traditional concrete kerb would have extended the contract period and caused further complications during installation.

After product searches and discussions, Scan Kerb was proposed as a much quicker and less disruptive alternative

Scan Kerb

Scan Kerb is a reinforced concrete stick down kerb which has highways agency approval under (section 1101 paragraph 2 of Highway works.)

Scan Kerb Type B

The standard B1 kerb (half batter profile) is delivered to site with the adhesive pre bonded to the underside of the kerb, the only preparation is to sweep the highway to remove dust and debris, prime the premarked kerb line with Scan coat, and bed the kerb in place, in cold weather it may be advisable to heat the road surface and underside of kerb to help speed up the adhesion process.

No breaking out or excavation was required for this project, the contractor was able to simply stick the kerb to the existing road surface

The key factors effecting the choice of Scan Kerb on this project, was the short contract period, and maintaining 24 hour store access. The lack of excavation and plant requirement, and Scan Kerb availability, enabled the contractor to complete the project on time and to the satisfaction of the client and clients agent.

To complete the pavement, the newly positioned Scan Kerb, was used as a shuttering for concrete to be poured behind the kerb to form the pavement surface

Project completed January/February 2010

Scan Kerb

Points of Interest

  • Quick installation required
  • No disruption to the store 24 hour access required
  • Wanted to remove the need for heavy plant and excavation
  • Client wanted a quick high quality solution

Product: Scan kerb Type B

Scan Kerb Type B

Quantities:

Scan Kerb Type B1- 87No.
Scan Coat 5Litre – 2No.
Scan Strip – 8No.

Project Team

Tesco
White, Young, Green – Cardiff
Dean & Dyball
Civil Engineering – Plymouth

Kerbs
Commercial Paving
Street Furniture